Adelong Swimming Complex - Tumut Shire Council
"Extracts from Tumut & Adelong Times April 16,2013
With construction commencing just under two months ago, the project is on schedule, and progressing well, with the former bowling green site now unrecognisable as extensive excavation works have transformed the area in readiness for the construction phase of the operation.
The bulk of the excavation is now complete and next week we will be starting to lay filtration pipe and pool reinforcement.
We will also be commencing on services, water, gas, sewer and storm water and pouring the building slab. The weather has certainly been in our favour
Icon is utilising local contractors where feasible, it is important to support local businesses.
Mitchbrook Mason has been fantastic doing all the excavation work for us and our concrete contractor Darrell Buckley is also local. We are trying to keep local as much as possible in all facets of the project"
Written by Robyn Bright - Tumut & Adelong Times
2013 will see Icon Building Group commencing this project to design and construct a new pool complex at Adelong, for Tumut Shire Council
This project will consist of a fully tiled concrete six lane 25m pool, program pool and wading pool with beach entry (walk-in). Water play splash pad, amenities, undercover and elevated viewing areas, shade sail area
To keep upto date further details coming at Commercial Projects
The Parkes Swimming Pool Upgrade
Commenced April 2012 - Completed Oct 2012
Recently completed Parkes Shire Council pool complex upgrade
Council major requirement to have the pool reopened in time for the summer season - Pool reopened October 2012
New and Improved
- Adding new childrens play pool area, including new splash toys for the enjoyment of kids of all ages
- Upgrading 50m pool
- New shade sails over new childrens play pool
- Adding new tiered seating along 50m pool
- New drained concourse and landscaping
- New pump area
- New solar heating
CURRENT PROJECTS:
Bringelly - New Home
Leppington - New Home
Oatley - New Home
Northbridge - Alteration and Additions
North Bondi - Aleteration and Additions
RECENTLY COMPLETED PROJECTS
New Homes:
Middeton Grange - Completed 2012
Harrington Park - Completed 2012
Cremorne - Completed 2011
Oatley - Completed 2010
Grasmere - Completed 2010
Alteration and Additions to Existing Homes:
Vaucluse - Renovation - Compeleted 2012
Waverley - Alteration and Addition - Completed 2012
Camperdown - Renovation - Compeleted 2012
Catherine Fields - Alteration and Addition - Completed 2012
Padstow Heights - Alteration and addition to rear of existing home - Completed 2012
Commercial Project:
Parkes Swimming Pool Upgrade - Completed 2012
Camden - Gledswood Winery/ Resaurant - Completed 2009
Industrial Project:
Smeaton Grange - Warehouse and Offfice - Completed 2010